The team was great. All bracing and walls were complete before we began. We could have been finished earlier - but we had to wait for the last truck load.
52.5 meters of concrete. As we said earlier - Fort Knox North.
Muniz and Mike gave a hand with some of the concrete work. The team only blew out one small wall as it was not fully braced.
Everyone is taking Sunday off - and Monday we will being taking the forms off, then drain tile etc.